NABARD RIDF Tranche XX - 2014-2015
- No. of Projects - 23
- Total Amount - 25.98 Crore
- No. of Projects completed - 0
- No of Ongoing Projects - 23
Sl No. |
Name of the Project |
AS amount |
Physical status |
Photographs |
---|---|---|---|---|
1 |
Construction of Government model fish farm (8 ponds), Edakochi |
1200 |
Work in Progress |
View Photo |
2 |
Construction of new building for Keecheri CHC |
161.94 |
Work in Progress |
View Photo |
3 |
Net mending yard at Kollemkode |
21.21 |
Work in Progress |
View Photo |
4 |
New academic block for GHSS,Vettoor |
207.28 |
Work in Progress |
View Photo |
5 |
New academic block for Govt. LPS, Sasthamkovil |
136.2 |
Work in Progress |
View Photo |
6 |
New academic block for Govt. UP School, Cherkol |
103.69 |
Work in Progress |
View Photo |
7 |
New academic block for kootikkada Govt. LPS and pre-primary school |
110.56 |
Work in Progress |
View Photo |
8 |
New academic block for Kumarapuram LPS, Karuvatta |
151.02 |
Work in Progress |
View Photo |
9 |
Construction of a PH subcentre in ward No. 12 in karuvatta |
21.73 |
Work yet to Commence |
View Photo |
10 |
Construction of new building for PHC, Kuzhipally |
191.35 |
Work yet to Commence |
|
11 |
Net mending yard at Prayikkara |
21.7 |
Work yet to Commence |
|
12 |
Locker rooms for OBM keeping at Puthiyangadi |
55.23 |
Tendered |
|
13 |
Net mending yard at Thrikkanad |
22.69 |
Tendered |
|
14 |
Construction of a Public toilet at Thrikkunnapuzha |
6.4 |
Pre-project activities in progress |
|
15 |
Construction of building for Anganvadi No.115 , ward no. 14,Thrikunnapuzha |
6 |
Pre-project activities in progress |
|
16 |
Construction of building for Anganvadi No.118 , ward no. 16,Thrikunnapuzha |
6 |
Pre-project activities in progress |
|
17 |
Construction of building for Anganvadi No.135 , ward no. 17,Thrikunnapuzha |
6 |
Pre-project activities in progress |
|
18 |
Construction of compound wall and ground filling at Fisheries hospital, panoor |
12.8 |
Pre-project activities in progress |
|
19 |
Mounting of high mast lights 3Nos.@ 8lakh at mala |
24 |
Pre-project activities in progress |
|
20 |
Mounting of high mast lights 3Nos.@ 8lakh at Poothotta |
24 |
Pre-project activities in progress |
|
21 |
Mounting of high mast lights 3Nos.@ 8lakh at udeyamperoor |
24 |
Pre-project activities in progress |
|
22 |
Mounting of high mast lights 3Nos.@ 8lakh and Rural Electrification at Karuvatta |
42.8 |
Pre-project activities in progress |
|
23 |
Net mending yard at Alappad |
41.36 |
Pre-project activities in progress |
|
Total |
2597.96 |
|