Projects

Installation of Highmast Light

  • No. of Projects - 51
  • Total Amount - 11.39 Crore
  • No. of Projects completed - 25
  • No of Ongoing Projects - 26
Sl No Project Outlay
(Rs. in lakh)
Status Photographs
Thiruvananthapuram
1 High mast light installation at Pallithura 32 Work Completed  
2 High mast Light, Valiyathura 13.58061 Work Completed
View Photo
3 Installaltion of highmast light in Poonthura 24 Work Completed
View Photo
4 Installation of High mast light at Kannamthura 40 Work Completed
View Photo
5 Installation of high mast light at Mampally 32 Work Completed  
6 Installation of High mast light at Valia veli 17 Work Completed  
7 Installation of high mast light in Puthukurichi 9.5 Work Completed
View Photo
8 Installation of High mast lights at Thiruvananthapuram (10 Nos) 70 Work Completed
View Photo
9 Installation of highmast light in Vizhinjam 52 Work Completed
View Photo
10 Installation of non soalr high mast light in Paruthiyoor 24 Work Completed
View Photo
11 Installation of solar street lighting at Pallithura 20.5 Pre-project activities in progress  
Kollam
1 High mast light installation at Alappad 16 Work Completed  
2 Installation of High mast lights at Kollam (2Nos) 14 Work Completed
View Photo
3 Installation of non solar high mast light in Thankassery 24 Work Completed
View Photo
4 Installation of Solar High mast light at Eravipuram 20 Work Completed
View Photo
5 High mast light installation at Thekkumbhagom and Thevalakkara 16 Work in Progress  
Alappuzha
1 Installation of non solar high mast light in Pallithode 14 Work Completed
View Photo
2 Installation of solar high mast light in Arthungal 14 Work Completed
View Photo
3 Installation of solar high mast light in Kattoor 14 Work Completed
View Photo
4 Installation of High mast lights at Alappuzha (3 Nos) 21 Work in Progress
View Photo
5 Installation of non solar high mast light in Arthungal 7 Work yet to Commence
View Photo
6 Installation of non solar high mast light in Kattoor 7 Work yet to Commence
View Photo
7 Mounting of high mast lights 3Nos.@ 8lakh and Rural Electrification at Karuvatta 42.8 Pre-project activities in progress  
Kottayam
1 Highmast light installation at Vaikom 16 Pre-project activities in progress  
Eranakulam
1 Installation of non solar high mast light in Udayamperror 21 Work Completed
View Photo
2 Installation of solar high mast light in Kumbalam 21 Work Completed
View Photo
3 Installation of non solar high mast light in Pallippuram 14 Work yet to Commence
View Photo
4 Mounting of high mast lights 3Nos.@ 8lakh at Poothotta 24 Pre-project activities in progress  
5 Mounting of high mast lights 3Nos.@ 8lakh at udeyamperoor 24 Pre-project activities in progress  
Thrissur
1 High mast Light, Anapuzha 8 Work Completed
View Photo
2 Electrification at vadanapally 29.91 Work in Progress  
3 Installation of High mast lights at Thrissur (1 Nos) 7 Work in Progress
View Photo
4 High mast light installation at Vadanapally 24 Pre-project activities in progress  
5 Installation of Solar High mast light at Blangad 20 Pre-project activities in progress
View Photo
6 Mounting of high mast lights 3Nos.@ 8lakh at mala 24 Pre-project activities in progress  
Malappuram
1 Installation of solar high mast light in Paravanna 14 Work Completed  
2 Installation of high mast light in Paravanna 21 Work yet to Commence  
3 Installation of non solar high mast light in Ariyalloor 28 Work yet to Commence  
4 High mast light installation at Koottayi 16 Pre-project activities in progress  
Kozhikode
1 High mast light, Beypore and Marad 14.1 Work Completed  
2 Installation of High mast lights at Kozhikkode (3 Nos) 21 Work Completed  
3 Installation of non solar high mast light in Elathur 14 Work yet to Commence  
4 Installation of non solar high mast light in Koilandy 24 Work yet to Commence  
5 High mast light installation at Madapally 32 Pre-project activities in progress  
6 Installation of High mast light at Vellayil 20 Pre-project activities in progress
View Photo
Kannur
1 Installation of High mast lights at Kannur(1 Nos) 7 Work Completed  
2 Installation of non solar high mast light in Chalil Gopalpetta 35 Work Completed
View Photo
Kasaragod
1 Installation of high mast light in Kottikulam 14 Work yet to Commence  
2 Installation of highmast light in Bengara Manjeswaram 14 Work yet to Commence  
3 High mast light installation at Kasaba 56 Pre-project activities in progress  
4 High mast light installation at Koippadi 32 Pre-project activities in progress